Nursery Plants Poly House Demonstration Womens Aam Shabha Water Harvesting Tanks World Bank Visit High Yielding Agriculture Crops Veteranary camp Training Programme for womens Agribusiness Alternate Energy-Pine Briquettes



UDWDP >>  UDWDP More Details

LEGAL COVENANTS APPLICABLE TO THE PROJECT
  1. Project Steering Committee - Establish and thereafter maintain throughout the period of implementation of the Project, a state-level steering committee.
  2. WMD Multi-disciplinary teams at district level- For each district involved in the Project, designate and thereafter maintain throughout the period of implementation of the Project, a multi-disciplinary team.
  3. Project internal Auditor - Hire by no later than six (6) months after the Effective Date, an internal auditor, under terms of reference acceptable to the Association.
  4. Project computerized accounting system- Establish by no later than three (3) month after the Effective Date, and thereafter maintain throughout the period of implementation of the Project, a computerized accounting system.
  5. Interim Financial Report- Furnish to the Recipient and the Association, not later than forty-five (45) days after the end of each calendar quarter, an interim financial report.
  6. Operational manual and safeguards instruments - The Project Implementing Entity shall implement the Project in accordance with the Operations Manual, ESMF and each environmental management plan and/or social management plan prepared there under, and TAP.
 
SAFEGUARD POLICIES APPLICABLE TO THE PROJECT
  1. Environmental Assessment OP/BP 4.01
  2. Natural Habitats OP/BP 4.04
  3. Forests OP/BP 4.36
  4. Pest Management OP 4.09
  5. Physical Cultural Resources OB/BP 4.11
  6. Indigenous Peoples OP/BP 4.10
  7. Involuntary Resettlement OP/BP 4.12

The application and mitigation of all the safeguard policies are covered in the Environmental & Social Management Framework (ESMF) applicable to the Project.